The Nome Nugget - Alaska's Oldest Newspaper

July 29, 2010

Nome Weather
Click here to buy photo

BACKYARD VIEW — Anvil Mountain with its signature rock formation and the White Alice towers to the right. See story on back page. Photo by Nadja Roessek

 


WONDER WOMAN?– Skydiving instructor Lindsay Widdall shows how it's done at a skydiving exhibition
in Nome last week. Photo by Denise Olin


 




Cover

• NJUS five-year sewer, water plans set
• Port Commission OKs RFP for port, harbor development plan

Page 2
• Editorial • Letters

Page 3
• News from around the state

Page 4
• Port and harbor development - continued from page 1
• NJU - continued from page 1

Page 5
• Late chum salmon run breaks record at Kwiniuk River tower

Page 6
• Plantar warts
• Obituaries

Page 7
• Obituaries - continued from page 6

Page 8 
• GPAA Cripple River Camp guests find riches beyond
the gold


Page 9 
• Lure of gold - continued from page 1

Page 10
• Man hit by cab

Page 11 
• UAF lists region's honors students for spring 2010

Page 12
• Classified Ads • Employment
• Legals • Trooper Beat • Seawall

Page 13
• More Legals - continued from page 1

Page 14
• Research ship visits Nome
• More Letters - continued from page 2
• Court
• Serving the Community of Nome

Page 15
• Serving the Community of Nome

Page 16
• White Alice waits for shoe to drop


NJUS five-year sewer, water plans set

By Sandra L. Medearis
Nome Joint Utility System board members have approved a plan that will direct the extension and upgrades of sewer and water services over the next five years.

The plan, put before the panel at a meeting July 20, looks at the current system and predicts growth and resources to order capital projects expected to total $27.7 million. "We have a to-do list. The sequence could be impacted by other federal or private projects," John K. Handeland, utility manager said. He added that the plan schedule itself had been driven in part by the need to have solid plans to back up funding applications due to state agencies in August.

NJUS has been working from a 2004 update of the 1996 five-year plan. Contract planners used a predicted one-percent-per-year growth rate in designing plans for the 20-year life of proposed sanitation improvements. Based on the state demographer's estimate, Nome had a population of 3,468 in 2009. Using a growth of one-percent per year, estimates show Nome with 3,681 in 2015 and in 2030, 4,274 people.

Top priority work will be in full swing next summer—first phase multi-million dollar project to replace failing, direct buried "Sclaircore" water and sewer piping installed on the east side of Nome in the early 1980s. Sclaircore? That's pre-insulated heat-traced pipe. This work will extend through 2014. The project also involves rebuilding the Sixth Avenue Pump House.

This summer crews are working along Nome Bypass to hook up the new hospital. Overhead work has finished. Now the operation has gone underground with a horizontal directional drill crew helping NJUS get a length of the hospital service buried. The utility is negotiating agreements with state Dept. of Transportation to let work get underway to reroute lines in preparation for a new, rerouted Snake River Bridge. The horizontal directional drill, just arrived on the most recent barge, will bore beneath the river channel near both the existing and proposed Snake River bridges as the least disruptive approach to replacing utilities currently suspended under the old bridge. With minimal disruption in existing routing, no cost of operation or additional freeze protection requirements will be necessary, according to analysis by CE 2 planning engineers. Expected to be finished in 2011, the utility relocation cost estimate is $2.3 million. Year 2011 work projects have a projected cost of $6.13 million.

In 2012, the plan calls for continued work, Phase II, of east Nome water and sewer replacement and expansion; a water and sewer telemetry system to insure secure security and allow monitoring and control of selected facilities and system elements; identification of a new water source—drill test wells, get site control, and design a transmission line from the source to a connection with the existing system. The total for proposed 2012 construction season: $4.5 million.

In 2013, the work will continue to Phase III east Nome water and sewer replacement and expansion; Seppala continued on page 4

Port Commission OKs RFP for port, harbor development plan

By Laurie McNicholas
The Nome Port Commission unanimously approved the final draft of a request for proposals to prepare a port and harbor development plan at a regular meeting July 22. The project is budgeted at $30,000 and includes the following scope of work.

  1. Feasibility of increasing the depth of the causeway to at least -35 feet mean lower low water, preferably to -40 feet.
  2. Options regarding design and development of an additional third dock on the causeway.
  3. Potential for expansion of the existing barge ramp to accommodate more vessels during heavy traffic periods.
  4. Strategies to attract vessels for increased use of Nome as a port for oil exploration and drilling in the Chukchi Sea.
  5. Study of tariff rates for the port and harbor and recommendations for any changes.
  6. Study to determine if additional mooring dolphins are needed just inside the breakwater area of the port.
  7. Efficient use of the limited space in the inner harbor.
  8. Potential for expanding up the Snake River with additional small boat moorage.
  9. Land use plan of the developed uplands area south and west of the small boat harbor and expanded area on the port pad.
  10. Potential for providing lighting, shore power and telecommunications to vessels dockside at both the small boat harbor and causeway.
  11. Strategies to attract tourist activities to the port and harbor.
  12. Increased security measures to meet existing U.S. Coast Guard regulations.
  13. Strategies to become a base for emergency oil spill and rescue response.
  14. Increased hub for fisheries and other research efforts in the Arctic.
  15. Identify local, state and federal regulations and treaties and implementation recommendations.
  16. Implementation plan on how to proceed with recommendations in the plan, including timelines and possible funding sources. continued on page 4

This web site requires Acrobat Reader